Walked in with an allowance of 60 lineal metres and was happily informed by slab supervisor James that we had only used 14.1
Our soil tests indicated weathered shale approx. 500mm below the surface and this has proven to be a great outcome for us
Look at the baby .2m pier (awaiting concrete)! We had mainly pier depths of .2, .3 and .4m
Slab supervisor and concreter overseeing the works
Slab is scheduled for Wednesday 20th November, followed by frame delivery on Monday 25th November.
I have started becoming an avid weather watcher, and unfortunately it looks like we've got a few wet weeks ahead of us
Lucky you merrynamy, you hit the jackpot when you bought your block hey? So glad to see everything went well for you, wowsers I can't believe the massive difference in pier total you ended up with congrats. Fingers are crossed for you for the 20th, I hope that goes well for you too best of luck.