Thursday, January 30, 2014

Progress Update

Looks like we've got some busy weeks ahead of us!

Electrical rough in was completed this week and our bricks are being cleaned today.

Insulation will be going in Monday with gyprock hopefully starting on Tuesday. Our SS Mark advised we'll probably be locked out in a 2-3 weeks :-(

We continue to have no luck with our glass stacker door - this time a panel has fallen out and shattered everywhere, ughhh. Mark is all over it though and we'll have a shiny new door installed shortly.

Clean bricks, ahhhhh





Saturday, January 25, 2014

Timber Beams Installed

So. damn. pretty.

I think they'll look ever better once they're stained and the front door/garage door are installed



Friday, January 24, 2014

Eaves Complete

What a difference eaves make!

Work started on our timber beams today too - can't wait to see the finished product


Thursday, January 16, 2014

Brickwork Completed

Brickies finished up yesterday and the exterior of our house is almost complete.

The splayed pillars look lovely and I bet they'll be even better once they're painted and the timber beams are installed.

Now the bricks just need a good clean ;)

Our holes in the mortar have been patched as well, phewwwww













Tuesday, January 14, 2014

Brickwork Continues Pt. 4

 
Brickwork is almost completely finished, just waiting on the small details around the windows as well as our pillars on the front patio (these will be bagged and painted)
 
Right now I'm so glad we never considered anything like a polished concrete floor - the slab is disgustingly messy with concrete dropped in several places and chips from fallen bricks.
 
Something I did not get a photo were some holes I've noticed in our mortar - very tiny holes that are perfectly round, almost as though drilled. After some careful Google investigation, it seems as though we may have mortar wasps or bees :( Has anyone dealt with this before?
 
 
 Front pillars begin
 
 
Alfresco area
 
 
 
 
 

Wednesday, January 8, 2014

Brickwork Continues Pt. 2

Brickies are roaring along now and have almost wrapped their way around the entire house.
Scaffolding was erected today so that brickwork can be completed up to the roofline.

Most of the work done now is in Bowral Simmental Silver - another completely solid brick that proved to be thousands of dollars cheaper than having Bowral Blue everywhere. We loved a Bowral Blue so much that we couldn't let it go entirely and instead chose to have it all across the front facade.

I know that having two different bricks will certainly not be to everyone's taste, but to us it was a good compromise given 1) the significant price difference, 2) the articulation joints would be 'hidden' by downpipes and fences  & 3) the  sides of the house would be rarely seen anyway and it would be a waste to spend $13k upgrading to bricks we would never really see

Articulation joint - will have a downpipe along the seam and will probably have a gate/fence around this area


Brickwork along the left side of the house


Brickwork along the rear of the house (home theatre, bedroom 4, alfresco)